Funding Plan Not ready Yet , YEIDA Fines Film City Firm

SHARE:

Noida: Yamuna Expressway Industrial Development Authority (YEIDA) has imposed a penalty on Bayview Bhutani Film City Private Limited — the concessionaire for the 230-acre Film City project — for failing to achieve “financial close” within the mandated six-month period.YEIDA officials said June 9, 2025, was fixed as the project’s “appointed date” after the authority approved the plot’s layout and the Phase 1 building plan for filming facilities and the film institute. That date set off the 180-day clock for financial close, making Dec 6 the cut-off.ccording to officials, financial close requires documentary  ..fter June 9, 2025, they had 180 days to furnish this. Under  ..

 