As of July 2026 the government was monitoring 1,775 ongoing central sector infrastructure projects with a combined estimated cost of Rs 37.11 trillion (tn) on the PAIMANA platform of the Ministry of Statistics and Programme Implementation. The ministry said 36 projects were added during the month an..
The ministry reported that 675 projects, or around 38 per cent, had reached more than 80 per cent physical progress while 305 projects, or about 17 per cent, had crossed 80 per cent financial completion, reflecting a mix of early stage and near completion works. The transport and logistics sector he..
At departmental level the Ministry of Road Transport and Highways had 993 projects, representing 56 per cent of tracked schemes and a revised cost of Rs 9.62 trillion. The Railways had 190 projects worth Rs 6.38 trillion and the Ministry of Coal had 121 projects costing Rs 2.22 trillion. Projects re..
The 36 newly monitored projects comprised 16 from the Department of Telecommunications, nine from the Ministry of Steel, six from Road Transport and Highways, three from the Ministry of Commerce and Industry and one each from the Ministry of Housing and Urban Affairs and the Ministry of Power. Key a..